Below is a the schedule for the del Lago roofing project. The first page shows a color-coded diagram of the del Lago, and two pages show the schedule by color. Identify your unit on the map, then look at the schedule. For example, address 3124. has a green circle with the number 8. Looking below, I see the work is projected to start on 9/25/2026 and completes on 10/15/2026.
All schedules are subject to change due to weather or materials, but Ryan hopes us to remain on or close to schedule. Currently we are only showing the Phase 1 schedule. Updates will be posted and sent out via email to del Lago residents who have registered their email.